Bison Drive Extension, Waverley Intersection & Pathways

I receive many calls asking:

  • When will the west end of Bison Drive connect through Waverley to the east end of Bison Drive ?
  • When will you build a pathway along the west side of Waverley from the Grand Mosque to Abinojii Mikanah?
  • I live on the west side of Waverley,  I want to bike to Superstore, Pembina Hwy, and the U of M – when are you going to build a pathway ?

The following overview provides a good breakdown of what needs to occur in order to make these critical east – west connections.

 BIG PICTURE:   CITY’S TRANSPORTATION MASTER PLAN 2050:

The City of Winnipeg Charter requires that city development plans be reviewed and re-adopted/replaced every five years. The Transportation Master Plan is one of the a key plans that must be updated as part of the reviews.  After nearly five years of researching (with pandemic in the middle), talking to Winnipeggers, and drafting strategies, the public works department (who is overseeing the study)  is ready for the public to review the final draft. Transportation Master Plan 2050 is the city’s master plan for moving Winnipeg’s transportation system forward. The plan is a comprehensive strategic document that outlines the methods and means to move our city and people into the future. Our population is expected to grow by more than 200,000 people by 2050. As our numbers grow, our demographics change. So do our priorities and the way we want and need to move around our city.

The Transportation Master Plan 2050 identifies city-wide transportation priorities for road & bridge infrastructure, transit infrastructure and routes, pedestrians and cycling routes, and trucking routes.  Specific to upgrading / building new roads &  bridges, the engineers & planners are recommending these 5 projects as the top priorities, to be either started, or completed between 2024-2033.  In alphabetical order:

  1. Arlington Bridge
  2. Bison Drive
  3. Chief Peguis Extension
  4. Louise Bridge
  5. Route 90

Today, all of these projects are in various stages of study and none of the five priorities are fully funded. You can see these location on a city wide map on page 35 – in the Short Summary of the Plan.

SPECIFIC TO WAVERLEY WEST

Planning the Bison Drive Extension & Waverley Intersection

Bison Drive, between Frontier Road & Waverley Road has been identified as a ‘short term 2024-2033’ priority. The Bison Drive extension requires the design and construction of an upgraded intersection at Bison and Waverley and active transportation infrastructure.  Funding has been secured

to undertake a study to examine potential intersection designs at Bison and Waverley to accommodate existing and future traffic volumes, and to incorporate active transportation infrastructure.

  • The scope of the study will include an examination of traffic requirements, drainage implications, utility conflicts and property requirements in order to develop designs for the intersection (round about, three way intersection, four way intersection, etc.)
  • The designs will be evaluated and a recommended intersection design and active transportation routes will proceed to a preliminary design phase.
  • The study is starting in 2025 and is anticipated to take one year to complete.
  • Upon completion, a Class 3 cost estimate will be developed and external funding sources will be identified for future budget consideration.

PLEASE NOTE: I know many would like to see the Bison Drive extension and intersection upgrade constructed ASAP because there is no east west connection to the U of Manitoba or to the Pembina Highway commercial businesses. In my opinion, it was poor planning not to build out Bison when the Bridgwater Forest development was occurring, but, am picking up the pieces. Currently, the only east west major connections out of the Bridgwaters, South Pointe and Prairie Pointe are at Kenaston / Abinojii Mikanah and at Kenaston and the Perimeter. We see the backlog of traffic exiting at Kenaston / Abinojii Mikanah, with most turning east. Again, IMO, its poor planning to add an entire neighbourhood on to the side of existing city with no mid-way –  east west connection.

Also see Item #3, page 9 in the Administrative Report

 Active Transportation (pathways and sidewalks)

During the design stages of the Bison Drive extension, the engineers will review where active transportation pathways should be constructed. The pathways will be constructed at the same time as the Bison Drive extension and the intersection upgrade occurs. I anticipate this construction will include:

  • a multi-use pathway along the west side of Waverley from John Angus to Abinojii Mikanah,
  • a multi use pathway on either the south side of Bison, connecting to the pathway network in front of Superstore – or on the north side of Bison, connecting with the pathway that leads into Waverley Heights.

PLEASE NOTE: these pathways will be constructed simultaneously with the construction of the Bison Drive extension and Waverley intersection. I know many would like to see the pathways constructed ASAP because there really is no separated east west connection to the U of Manitoba – the most highly commuted to destination in the south, but this is not possible as all components of this project will be done together.  

 When will the Bison Drive Extension & Waverley Intersection be constructed?

  • Everything depends on securing funding.
  • The City will have a class 3 estimate of cost by 2026.  I have no idea what the project might cost – but I would guess around $30+ million.
  • Significant funding has already been set aside by the developers of Bison Run & the Bridgwaters. The City now must come up with a portion of the funding.
  • There are 5 projects, worth hundreds of millions,  that have been prioritized, but in no particular order.  Many of the 5 projects will not proceed unless funding is secured from other levels of government.
  • The Bison Drive Extension – Waverley Intersection project is anticipated to be funded in its entirety by the City.

I’d like to say this critical east – west link will be constructed within the next 10 years, but I really can’t say this with certainty. The Transportation Master Plan 2050 has identified it as one of the top 5 priorities.