Pathway Construction
You will notice that pathways leading to the retention ponds around Rose Lake are currently closed. The developer- Manitoba Housing is doing work in the area to landscape and re-grade to improve the drainage adjacent to the pathways. Work is also being done with the native grasses in the area surrounding the retention ponds.
The paths are closed to allow light machinery to access the site and to ensure the safety of residents as it is a construction site.
A specific timeline cannot be confirmed as work can be paused due to weather and in certain cases the one project may have to wait until certain work is completed on the other project to continue their work. Mantioba housing’s estimate is that the landscaping and drainage work will be complete in 4-6 weeks allowing the paths to be open again.
For more information please contact bridgwaterdevelopment@gov.mb.ca