Construction Notice – Glenacres Cr – Millstream Wy to Millstream Wy

2022 LOCAL THIN BITUMINOUS OVERLAY (TBO) PROGRAM GLENACRES CR – MILLSTREAM WY to MILLSTREAM RD

The above Thin Bituminous Overlay (TBO) project has been approved for construction as part of the City of Winnipeg’s 2021 Local Street Renewal Program. See the letter sent to residents.

  • Construction Start: May 18, 2022
  • Duration: Three weeks
  • Traffic implications:
    • Restricted on-street parking
    • Reduction to one lane for local access vehicular traffic

As part of this work, the contractor will adjust catch basins and manholes, minor concrete maintenance repairs, replace missing and damaged curbs, repair sidewalks as needed, restore the boulevard as required.

During construction, on-street parking will be prohibited and one lane of two-way local-access traffic will be maintained. During some portions of the work, the street will be completely closed to traffic and private approaches will not be accessible. In these situations, you will be notified at least 24 hours prior to the disruption of access.

Garbage and recycling will continue to be picked up at regular locations and times. The contractor may relocate bins if required.
Anyone with accessibility needs, moving requirements, any underground appurtenances, such as sprinkler systems, lighting cables, etc. within 6 metres (20 feet) of the street curb line or any other questions are asked to contact Andrew Boboski from WSP Canada Inc. at (204) 477-7608, during regular working hours or by email at info.wpg@wsp.com.

If you have any questions about the project or have accessibility needs, please contact:

Andrew Boboski

WSP Canada Inc.

(204) 477-7608

info.wpg@wsp.com

 

Colin Titchkosky

City of Winnipeg

(204) 986-4883

CTitchkosky@winnipeg.ca