Construction Notice – Marygrove Cr – Columbia Dr to Columbia Dr

2021 LOCAL THIN BITUMINOUS OVERLAY (TBO) PROGRAM MARYGROVE CR – COLUMBIA DR to COLUMBIA DR

The above Thin Bituminous Overlay (TBO) project has been approved for construction as part of the City of Winnipeg’s 2021 Local Street Renewal Program. See the letter sent to residents.

Construction Start: September 23, 2021

Duration: Three weeks

Traffic implications:

  • Restricted on-street parking
  • Reduction to one lane for local access vehicular traffic

As part of this work, the City will adjust catch basins and manholes, repair concrete pavement, replace missing and damaged curbs, repair sidewalks as needed, restore the boulevard, mill the existing asphalt overlay and install a new asphalt overlay

During construction, on-street parking will be prohibited and one lane of two-way local-access traffic will be maintained. During some portions of the work, the street will be completely closed to traffic and private approaches will not be accessible. In these situations, residents will be notified at least 24 hours prior to the disruption of access.

Garbage and recycling will continue to be picked up at regular locations and times. The contractor may relocate bins if required.

If you have accessibility needs, moving requirements, any underground appurtenances, such as sprinkler systems, lighting cables, etc. within 6 metres (20 feet) of the street curb line or any other questions, please contact

Michael Spack

WSP Canada Inc

(204) 771-5082

Michael.Spack@wsp.com

Colin Titchkosky

Public Works Department, City of Winnipeg

(204) 986-4883

CTitchkosky@winnipeg.ca