2021 LOCAL THIN BITUMINOUS OVERLAY (TBO) PROGRAM PINCARROW RD – SCURFIELD BLVD to EGLINTON CR
The above Thin Bituminous Overlay (TBO) project has been approved for construction as part of the City of Winnipeg’s 2021 Local Street Renewal Program. See the letter sent to residents.
Construction Start: Week of May 17, weather permitting
Duration: Approximately three weeks, weather permitting
Traffic implication: Restricted on-street parking, reduction to one lane for local-access vehicular traffic
The work on Pincarrow Rd will include adjustment of catch basins and manholes, concrete pavement repairs, milling of existing asphalt overlay, replacement of missing and damaged curbs, renewal of curb ramps, localized sidewalk repairs, boulevard restoration, and asphalt overlay.
This work is being done in an effort to improve the ride and drainage on the street, as well as lengthen the service life of the pavement.
On-street parking will be prohibited during construction. One lane of local-access traffic as well as pedestrian access will be maintained. During some portions of the work, the street will be completely closed to traffic and private approaches will not be accessible. In these situations, you will be notified at least 24 hours prior to the disruption of access.
Garbage and recycling will continue to be picked up at regular locations and times. The contractor may relocate bins if required.
If you have any questions about the project or have accessibility needs, please contact:
Michael Turko
KGS Group
(204) 918-9536
mturko@kgsgroup.com